# | List of Project under Execution & executed |
Client | Consultant | Time of Award | Value at Award | Completion Date | Acual Completion Date | Location of Project |
1 | Extension of Water Pipeline at various parts in Ras Al Khaimah |
Federal Electricity & Water Authority [FEWA] | Federal Electricity & Water Authority [FEWA] | 6 Months | 2,500,000.00 | 25/04/2006 | 30/04/2006 | Ras Al Khaimah |
2 | Pumping Station & Pumping Main for Sheikh Faisal Building at Al Khan Area |
H. H. Sheikh Faisel | S. M. D. D. | 3 Months | 950,000.00 | 29/04/2006 | 29/04/2006 | Al Khan, Sharjah |
3 | R 490 Urben Development Projects – Internal roads in L. C. Housing in Tawi Nazwa |
Govt. of Sharjah | Consulting Architecture and Civil eng. Bureau | 4 Months | 1,250,000.00 | 30/11/2006 | 30/11/2006 | Tawi Nazwa |
4 | New Pumping Main from P. A. 1 to Treatment Plant at Ind. Area No. 5 |
Sharjah Municipality | S. M. D. D. | 17 Months | 10,000,000.00 | 31/01/2008 | 31/01/2008 | Ind. Area No.:5 |
5 | R – 357 Urban Development Projects – Internal roads L.C. Housing in IBN Rasheed |
Govt. of Sharjah | Directorate of Public Works | 15 Months | 12,767,300.00 | 28/02/2008 | 28/02/2008 | IBN Rasheed |
6 | Effluent Main and Pumping main with associated lift Station at Al Khan Heritage Area |
H. H. Dr. Sultan Bin Mohammed Al Qassimi | Cansult Maunsell | 6 Months | 1,115,850.00 | 30/04/2008 | 30/04/2008 | Al Khan, Sharjah |
7 | Construction of Pumping Main and pumping station at Ghubeibah Area, Shrjah |
Sharjah Municipality | S. M. D. D. | 12 Months | 14,000,000.00 | 31/12/2008 | 15/01/2009 | Al Ghubeibah, Sharjah |
8 | R 521 A – Construction of Slip roads at Jn. 68 -Emirates Road |
Govt. of Sharjah | Halcrow International Partnership | 45 Days | 2,775,560.00 | 30/06/2008 | 30/06/2008 | Jn- 68, Emirates road, Sharjah |
9 | R 596 -University City Clock Tower Roundabout slip roads, at University City – Sharjah |
Govt. of Sharjah | Halcrow International Partnership | 120 days | 11,000,000.00 | 15/02/2009 | 25/02/2009 | University City, Sharjah |
10 | Construction of S. W. Pumping Main from Dasman P. S. to existing P.M. in industrial area and P. S. in industrial area 3 |
Sharjah Municipality | S. M. D. D. | 12 Month | 11,000,000.00 | 30/06/2009 | 30/06/2009 | Dasman P. S to Industrial area 3, Sharjah |
11 | Re-routing of Pumping Main in Samnan Area | Sharjah Municipality | S. M. D. D. | 60 Days | 1,500,000.00 | 30/06/2009 | 30/06/2009 | Samnan, Sharjah |
12 | R-591 -SharjahLibrary Building – External Works | Govt. of Sharjah | Halcrow International Partnership | 50 days | 4,275,026.00 | 04/03/2010 | 04/03/2010 | Sharjah |
13 | Maintenance work for Court Roads in Khorfakhan | Sharjah Municipality | Directorate of Public Works | 90 Days | 2,249,768.00 | 10/04/2010 | 10/04/2010 | Khorfakhan |
14 | Extension of Ajman Sewerage Network (Phase one) – 108 Plot sewer house connection in Basin 5, 6, HA, 17 & 18; another 70 plots connection at ASPCL area |
Ajman Sewerage (P) Cpmpany Ltd. | Halcrow International Partnership | 12 Month | 5,792,835.00 | 01/12/2010 | 01/12/2010 | Basin 5, 6, HA, 17, 18 & other locations in ASPCL area, Ajman |
15 | Irrection of Water Tank at Al Wahadha Street | Sharjah Municipality | Sharjah Municipality | 30 Days | 202,350.00 | Al Wahadah, Sharjah | ||
16 | Maintenance work for Anjad Round About Roads in Khorfakhan |
Govt. of Sharjah | Directorate of Public Works | 7 Days | 73,275.00 | Khorfakhan | ||
17 | R 684 U-turn & Pedestrian crossing at Al Nadha Area |
Govt. of Sharjah | Directorate of Public Works | 14 Days | 282,050.00 | 02/05/2011 | 02/05/2011 | Al Nadha, Sharjah |
18 | R696 Neighbourhood Shopping Centre car park at Al Goaz area. |
Govt. of Sharjah | Halcrow International Partnership | 45 Days | 1,625,000.00 | 02/09/2011 | 02/09/2011 | Al Goaz, Sharjah |
19 | R657 – Skyline College External Works for Men’s Hostal |
Govt. of Sharjah | Halcrow International Partnership | 45 Days | 1,104,000.00 | 25/09/2011 | 25/09/2011 | Uicersity City, Sharjah |
20 | Extension of Ajman Sewerage Network (Phase one) (Part II) |
Ajman Sewerage (P) Cpmpany Ltd. | Ajman Sewerage (P) Cpmpany Ltd. | 12 Months | 2,500,000.00 | 28/02/2012 | 28/02/2012 | Jarf, Other areas in Ajman |
21 | Package 5 External Services Infrastructure – Foul Water drinage works |
Sharjah Arts Foundation | Scott Wilson, Dubai | 4 Months | 693,450.00 | 14/04/2012 | 14/04/2014 | Sharjah Art Foundation, Sharjah |
22 | Asphalt Road & interlock parking for Sharjah Co-operative Socity, Al Qarayen |
Sharjah Co-operative Socity | Directorate of Public Works | 120 days | 2,100,000.00 | 10/05/2012 | 10/05/2012 | Al Qarayen. Sharjah |
23 | Re-construction of Asphalt Service Road in Al Wahada Road at Ramla area. |
Govt. of Sharjah | Directorate of Public Works | 28 days | 525,000.00 | 23/06/2012 | 24/06/2012 | Ramla, Sharjah |
24 | R 749 – Asphalt paving around Helipad in Al Badeya Palace, Sharjah |
Govt. of Sharjah | Directorate of Public Works | 21 Days | 1,050,000.00 | 30/08/2012 | 30/08/2012 | Al Badeya Palace, Sharjah |
25 | R 767 – re-construction of single lane of the existing C/way in Muwailah School area |
Govt. of Sharjah | Directorate of Public Works | 45 Days | 918,150.00 | 25/09/2012 | 25/09/2012 | Muwailah, Sharjah |
26 | R 754 – Parking & Footpath (rubber tiles)around al Manak Park |
Govt. of Sharjah | Directorate of Public Works | 45 Days | 723,000.00 | 31/12/2012 | 31/12/2012 | Manak, Sharjah |
27 | R 687 – Entrence to Industrial Area in Al Madam | Govt. of Sharjah | Directorate of Public Works | 40 Days | 1,518,185.00 | 11/02/2013 | 11/02/2013 | Al Madam, Sharjah |
28 | R676 – External works for Al Qarayen Mosque | Govt. of Sharjah | Katib & Alami | 45 Days | 1,473,524.00 | 30/05/2013 | 30/05/2013 | Al Qarayen, Sharjah |
29 | R 759 Road & Parking for Saeed Bin Jubar Mosque in Al Goaz |
Govt. of Sharjah | Directorate of Public Works | 100 Days | 1,704,438.00 | 15/06/2013 | 15/06/2013 | Al Goaz, Sharjah |
30 | Extension of Ajman Sewerage Network (Term Contract) 3rd Term |
Ajman Sewerage (P) Cpmpany Ltd. | Ajman Sewerage (P) Cpmpany Ltd. | 490 Days | 4,000,000.00 | 12/12/2013 | 25/12/2013 | Various Parts in Ajman |
31 | Sea Outfall Pipeline Project | Ajman Municipality | ASPCL / Tebodin | 8 Months | 19,932,944.00 | 31/05/2014 | 31/05/2014 | Jarf, Ajman |
32 | R848 Roads inside Maleiha Sports Club | Govt. of Sharjah | Roads & Transport Authority, Sharjah | 21 days | 1,400,000.00 | 29/04/2014 | 26/04/2014 | Maleiha (Dhaid – Madam Road) |
33 | R 708 – Hump Construction in various parts in Sharjah – 2014 |
Govt. of Sharjah | Roads & Transport Authority, Sharjah | Term Contract | 1,000,000.00 | 31/12/2014 | 31/12/2014 | Hump construction in various parts of Sharjah City. |
34 | Effluent Water Pumping Main in Al Ramaqia and Muwafjah |
Sharjah Municipality | S. M. D. D. | 120 Days | 1,046,500.00 | 25/05/2014 | 25/05/2014 | Al Ramaqia and Muwafjah |
35 | Connection of 225 mm effluent Water Pumping main to 400 mm Effluent pumping main in Al Mumzar Area |
Sharjah Municipality | S. M. D. D. | 75 Days | 600,000.00 | 99% Work completed | 99% Work completed | Al Mumzar Area, Sharjah |
36 | Treated Effluent Feed Pipeline to SAFI Treatment Plant |
SAFI FZC | ASPCL | 90 Days | 1,069,099.00 | 25/12/2014 | 25/12/2014 | Feeder line between Ajman Wastewater Treatment Plant & SAFI Treatment Plant |
37 | Extension of Ajman Sewerage Network (Term Contract- Addentum 5) |
Ajman Sewerage (P) Cpmpany Ltd. | Ajman Sewerage (P) Cpmpany Ltd. | 12 Months | 7,000,000.00 | 15/02/2014 | 25/02/2014 | Various Parts in Ajman |
38 | Package 6 External Services Infrastructure – Foul Water drinage works |
Sharjah Arts Foundation | Scott Wilson, Dubai | 4 Months | 450,000.00 | Work in Progress | Work in Progress | Sharjah Art Foundation, Sharjah |
39 | Chicago -Westminister School- Parking & Footpath Work |
GEMS Educations | Chicago Maintenance & Construction Co. | 21 days | 448,800.00 | 10/11/2014 | 10/11/2014 | Moeilah, Sharjah |
40 | R 809 – Parking within Plot No.: 769 – Abu Tina | Govt. of Sharjah | Roads & Transport Authority, Sharjah | 75 Days | 1,025,000.00 | 30/11/2014 | 30/11/2014 | Abu Tina, Sharjah |
41 | R 755 – Service Roads & Parking for Kalba Sports Club (Phase 1) |
Govt. of Sharjah | Roads & Transport Authority, Sharjah | 60 Days | 1,646,780.00 | 15/11/2014 | 15/11/2014 | Kalba, Sharjah |
42 | R 806 Internal Roads at Al Baraha area, Kalba | Govt. of Sharjah | Roads & Transport Authority, Sharjah | 120 days | 8,340,000.00 | Work in Progress | Work in Progress | Al Baraha, Kalba |
43 | Ajman Sewerage System – Sewerage NetworkJurf 1 University Area |
Ajman Sewerage (P) Cpmpany Ltd. | Ajman Sewerage (P) Cpmpany Ltd. | 356 Days | 9,044,650.00 | Work in Progress | Work in Progress | Jurf 1, Humadeya Area, Ajman |
44 | Storm Water Lifting Station & Associated Civil & MEP) works |
Shurooq – Sharjah Investment & Development Authority |
GAJ (Godwin Austen Johnson) | 90 Days | 2,893,700.00 | Work in Progress | Work in Progress | Heart of Sharjah – Souk Al Shanasiya, Sharjah |
45 | R 914 Special Arts Centre – Parking Arrangement | Govt. of Sharjah | Roads & Transport Authority, Sharjah | 14 Days | 50,550.00 | Waiting for NOCs | Sharjah |